Project 2010 - Auto level resource backwards RRS feed

  • Question

  • Hi Everyone,

    I suspect this isnt possible but here goes!

    I have several task that need to be completed by lunchtime on a monday. It doesnt matter if they are completed the previous friday or before, but they must be completed by monday lunchtime.

    Essentially I have delivery tasks that can finish no later than and collection tasks that start no earlier than. Its the delivery tasks I have an issue with.

    I have set these tasks to "finish no later" (I have also tried "start no later" etc) but when I level it still pushes tasks into monday PM and tuesday.

    How do I stop this from happening?

    Thanks

    Alex


    • Edited by cossie2know Wednesday, April 9, 2014 12:09 PM
    Wednesday, April 9, 2014 12:08 PM

All replies

  • Hi Alex,

    Try either to put the constraint "must finish on" or set a high priority on those task (priority field to 1000).

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    Wednesday, April 9, 2014 12:14 PM
    Moderator
  • Hi,

    Thanks for your suggestion. Unfortunately it doesnt seem to work. If I set them to priority 1000 they just stay in place. If I state must finish on it still pushes it to the right rather than the left.

    I think I will just have to put up with it

    Thanks again

    Alex

    Thursday, April 10, 2014 7:58 AM