  • We have created a Workflow in Project Server Using Visual Studio and its working fine. But when we tried to use the skip stage it is only skipping till the next approval stage. Sometimes we need to move the project directly to the last stage bypassing the approval stages.

    Any thougts is appreciated


    Thanks & Regards, Benno
    Tuesday, May 10, 2011 6:45 AM

Answers

  • Beno you need to insert if else statements in the workflow, check for variable "projectSequence.WorkflowContext.SkipToStage", below is the code I used to see if this is skip to stage or normal workflow is being processed.

    Let me know if you require more information.  

    private void IsSkipToStage(object sender, ConditionalEventArgs e)
        {
          e.Result = projectSequence.WorkflowContext.SkipToStage;
        }
    

    Mateen

    • Proposed as answer by Mateen Imtiaz Thursday, May 26, 2011 5:42 AM
    • Marked as answer by Benno EPM Thursday, May 26, 2011 7:20 AM
    Wednesday, May 25, 2011 9:25 AM

All replies

  • Beno you need to insert if else statements in the workflow, check for variable "projectSequence.WorkflowContext.SkipToStage", below is the code I used to see if this is skip to stage or normal workflow is being processed.

    Let me know if you require more information.  

    private void IsSkipToStage(object sender, ConditionalEventArgs e)
        {
          e.Result = projectSequence.WorkflowContext.SkipToStage;
        }
    

    Mateen

    • Proposed as answer by Mateen Imtiaz Thursday, May 26, 2011 5:42 AM
    • Marked as answer by Benno EPM Thursday, May 26, 2011 7:20 AM
    Wednesday, May 25, 2011 9:25 AM
  • Thanks Mimtiaz :)
    Thanks & Regards, Benno
    Thursday, May 26, 2011 7:20 AM