Make manual task Start, Finish or Duration blank through API RRS feed

  • Question

  • Hi,

    How can I make Start, Finish or Duration blank through API for a manual task in Project 2010 or 2013? The IsStartValid, IsFinishValid and IsDurationValid fields are read-only.

    Thanks,

    Sergey


    • Edited by Serg23 Thursday, December 6, 2012 9:24 AM
    Thursday, December 6, 2012 9:20 AM