Assign resourceto work 2 weeks and rest a week RRS feed

  • Question

  • Hello,

    I need help assigning project schedule to resources who have to travel to the client's site but they have to spend only 2 weeks rest 1 week and then come back. So the schedule timeline should adapt to this.

    I appreciate any help I can get.

    Friday, November 1, 2019 11:03 AM

Answers

  • KhoulaM --

    Why don't you create tasks named Onsite Work at Client Site with a Duration of 10 days, and No Work at Client Site with a Duration of 5 days?  Just a thought.  Hope this helps.


    Dale A. Howard [MVP]