Ideal trend is not displaying as expected and its almost flat RRS feed

  • Question

  • Hi 

    The Sprint Burndown report Ideal Trend showing flat. We assign two tasks to the current sprint and TFS calculate the ideal trend with only this two tasks. we add more tasks in TFS for the current sprint after few days but the ideal trend was not recalculated.

    Our environment is TFS 2015 Up3. Is there anyway we can get the Ideal Trend normal. Warehouse job is executing as expected verified jobs also other team reports as expected. 

    Can you please suggest here. 

    Thank you!!

    Durga 


    Wednesday, September 20, 2017 3:54 PM

All replies

  • Hi Durga,

    Could you please check whether you have set value of Remaining work field for new added tasks? The ideal trend is calculate remaining work hours.

    Best Regards  