Resource Pool File -- Team Planner RRS feed

  • Question

  • I am using a MS Project 2016 Pro Resouce Pool file to allocate resources to shared project files. When I look at the Team Planner view within the Resource Pool file, the horizontal task bar identifies the task and date range is filled with a very light gray color. It is difficult to determine the date range of the task with this fill color. How can I change the fill color of the bar in the Team Planner view with a Resource Pool file? Thanks in advance
    Tuesday, November 5, 2019 7:00 PM

Answers

  • USNA82,

    In the Team Planner view go to Format > Styles group. Select the desired item (e.g. Actual Work). That should bring a drop down that allows you to set the Border Color and Fill Color.

    Hope this helps.

    John

    Tuesday, November 5, 2019 8:00 PM