  • Hi,

    If you need cost per hours, it is probably related to a work resource, having a daily rate. If you need to manage cost per square feet, then it is not a work resource anymore but a material resource. You can create a new resource in the resource sheet with the type "material", specify "sq/ft" for the label and enter a rate which will be the unit cost (cost of 1 sq feet).