Customization in Project Server 2019 RRS feed

  • Question

  • Hi All,

    We are thinking of implementing PS 2019. There are certain customization that needs to be done. I just wanted to know whether it is possible or not:

    1. Once the Project has been baselined, it can't be overwritten. Except for the Admin.
    2. Can we have validations at the Project Level entity. e.g. - If i select a project is Billable in one field, then the field for type of projects should show only Fixed bid or Support and not any other master.
    3. Can we lock a set of tasks in a phase automatically once the phase has been completed 100%.
    4. If a resource has been assigned 100% for a day, can the resource be locked for that day in order to prevent overallocation

    Thanks in advance.


    Cheers, Amit Wairkar


    • Edited by Amit.Wairkar Tuesday, September 17, 2019 5:46 AM Adding 4th point
    Tuesday, September 17, 2019 4:49 AM