回答済み Duration vs Task Time

  • 2012年8月2日 下午 07:48
     
     

    I have a task that will only take 2 hours to complete. However, I want the duration to be 1 day.

    I have set the duration at 1 day. I changed the task type to "Fixed Duration". Then I set the "Resource Units" to 25%.

    Is this the bext way to do this, or am I going around the neighborhood to get next door?