Duration vs Task Time
-
2012年8月2日 下午 07:48
I have a task that will only take 2 hours to complete. However, I want the duration to be 1 day.
I have set the duration at 1 day. I changed the task type to "Fixed Duration". Then I set the "Resource Units" to 25%.
Is this the bext way to do this, or am I going around the neighborhood to get next door?
所有回覆
-
2012年8月2日 下午 07:55
Rgunterll,
Yup, that's probably the best way to do it. You're on the right track.
John
- 已標示為解答 Jan De Messemaeker - Project MVPMVP, Moderator 2012年8月3日 上午 08:22
-
2012年8月2日 下午 09:18Thank you John
-
2012年8月3日 上午 02:44
Rgunterll,
You're welcome. Please mark this as answered unless you have a related follow-on question.
John
- 已編輯 John - Project 2012年8月3日 上午 02:44