Microsoft Project 2007 - copy paste special link problems for multiple projects

Soru Microsoft Project 2007 - copy paste special link problems for multiple projects

  • 02 Ağustos 2012 Perşembe 14:59
     
     

    In Project Server 2007 opening multiple projects in Project Pro 2007, copying duration field and paste  special -Past link as text is not working.It is working for single project but not for multiple projects.

    Any help is appreciated.

Tüm Yanıtlar

  • 02 Ağustos 2012 Perşembe 19:57
     
     

    Jay4646,

    First of all, using paste links is playing with fire. They are the most prone to eventual file corruption. What exactly is your end goal?

    John

  • 02 Ağustos 2012 Perşembe 20:58
     
     

    John,

       You are right paste links is playing with fire . Most of  My users are copying duration cell and pasting ascspecial link another duration cell. The basic idea is to link two cell values, if one changed the other cell values replicates.  

  • 03 Ağustos 2012 Cuma 02:48
     
     

    Jay4646,

    If all they want to do is to copy the Duration field into an extra duration field (e.g. Duration1), a simple formula will do the trick and avoid the possible corruption issue. It will update as the Duration changes.

    Now back to my question. What is the end goal?

    John

  • 06 Ağustos 2012 Pazartesi 19:43
     
     
    Could you elaborate a little more about the corruption issue?  I'm working on a schedule where some of the exact same tasks are located in more than one place (my boss wants the master and sub schedules in the same file).  I was thinking of using the paste special so that I wouldn't have to go hunting through 1500 lines to find the 2 or 3 identical tasks to update at the same time.  I also figured it would save my behind in case I missed a line at some point.  Will paste special work ok within the same file or is there a better way to do this?
  • 07 Ağustos 2012 Salı 01:49
     
     

    SAR5,

    By their nature paste links are prone to corruption. The exact reason why, I don't know. And it doesn't matter if the paste links are within a given file or between files or even applications (e.g. Project links to Excel).

    Define what you boss calls a "master". You should not have identical tasks replicated in a file. There are much better and simpler ways to isolate selected tasks for reports and reviews. Filtering is one way, grouping is another.

    If you really want to "save your behind", I suggest you do not use paste links. They will work but using them requires an extreme amount of user and file discipline - something most users are not set up to manage.

    John