Fields or text in MS Project 2007/2010 Relationship Diagram

    Question

  • A user wants to add fields to the displayed text in MS Project's Relationship Diagram view. Specifically he wants to add lag to either the Task box or to the pred/succ line.

    Thank you.

    Tuesday, April 19, 2011 4:58 PM

Answers

  • Hi Joseph,

    I think it possible to change the display text on the Relationship Diagram via C#. I tried the MS Project PIA and the applicaiton object includes the SetTaskField method. You can set the text through this method.

    Hope this can help you.

    Best Regards,


    Bruce Song [MSFT]
    MSDN Community Support | Feedback to us
    Get or Request Code Sample from Microsoft
    Please remember to mark the replies as answers if they help and unmark them if they provide no help.

    • Marked as answer by jkormann Friday, April 22, 2011 3:26 PM
    Friday, April 22, 2011 5:19 AM