Answered Gantt of Resources in Team System

  • giovedì 12 luglio 2012 08:49
     
     

    Hello,

    Is there a way to manage my resources (employees, Rooms...) in a visual way as Gantt in Team system?

    I have Work Item tasks with estimation time but how can I know if my resources are available for that estimation?

    Thanks!


    lekfir

Tutte le risposte

  • giovedì 12 luglio 2012 13:13
     
     

    You can use MS Project to import/syncronice  your workitem data (time estimation) and use Project to manage your resources.
    There is also a simplier excel workbook for agile planing that contains a simple way for capacity planing and to make sure you dont over allocate your team.

  • giovedì 12 luglio 2012 17:59
     
     

    Thanks Mattias,

    Where can I find the Excel workbook?


    lekfir

  • giovedì 12 luglio 2012 20:43
     
     Con risposta

    Asuming you have a team project with MSF for Agile you will find them under the documents folder in the path \Documents\Shared Documents\Iteration 1\Iteration Backlog.xslm

    • Contrassegnato come risposta lekfir giovedì 12 luglio 2012 21:03
    •