Locked TFS 2010 Iteration backlog - Burndown. Not updating

  • venerdì 2 marzo 2012 08:56
     
     

    In my Iteration Backlog generated by TFS 2010, Burn-down chart is not updating with data.It is always showing the below error message.I have "\Iteration 1" in my team project.

    The iteration path '\Iteration 1' is not in the cube. Try again after you have a work item with this iteration path and the cube has been processed.

    Please help


    Searching...Searching....


    • Modificato AneeshSalim venerdì 2 marzo 2012 08:57
    •  

Tutte le risposte

  • sabato 3 marzo 2012 16:56
     
     

    Could you create a temp work item that contains iteration 1, process the cube, then re-run your report?

    Cheers

  • lunedì 5 marzo 2012 05:03
    Moderatore
     
     Con risposta

    Hi Aneesh,

    Thank you for your post.

    Would you please try to refresh the cube, for detail steps please refer to Manually Process the Data Warehouse and Analysis Services Cube for Team Foundation Server.

    If the issue, would you please go to event viewer to see is there any log relate to this issue.

    I hope this information will help resolve this issue.

    If anything is unclear, please free feel to let me know.

    Best regards,


    Lily Wu [MSFT]
    MSDN Community Support | Feedback to us

    • Contrassegnato come risposta AneeshSalim martedì 3 aprile 2012 09:07
    •