Sprint and Team field within the Sprint Burndown Chart page (TFS Conchango for VS2010)
-
mardi 21 décembre 2010 17:30We have recently upgraded to TFS Conchango fo VS2010 and have run into some learning pains. I attempted to run a sprint burndown chart but received an error since the Sprint and Team field was not completed. The problem is that the Sprint and Team dropdown is empty. We have looked at the Product Backlog and Sprint Backlogs and do not see anywhere to enter this information. Does anyone know how I can get data added to this dropdown?
Toutes les réponses
-
jeudi 23 décembre 2010 07:19Modérateur
Hello jh714,
Thanks for your post.
This article describes the similar issue as yours, could you please take a look at if it can resolve your problem?
Thanks,
Vicky Song [MSFT]
MSDN Community Support | Feedback to us
Get or Request Code Sample from Microsoft
Please remember to mark the replies as answers if they help and unmark them if they provide no help.

- Marqué comme réponse Vicky SongModerator lundi 27 décembre 2010 09:40
-
mardi 5 juin 2012 20:58
i know this is a really late post however i was having this same issue using a different template so thought i'd comment on my resolution..
We are using SfTS v3 templates and the "Sprint and Team" dropdown in the Sprint reports were empty.
To resolve this i found that our iteration paths were not structured properly.
After updating our iterations paths to the match the standard in the following post, it worked for us:
http://consultingblogs.emc.com/crispinparker/archive/2010/05/18/getting-started-with-scrum-for-team-system-version-3-tfs-2010.aspx
(See "Planning Scope" section)hope this helps someone else..