Refresh in MSP 2010 caused the tasked to disappear
-
Friday, June 22, 2012 8:44 AM
Hi,
I have created a project plan and published it on project server. I synchronized the plan with TFS and most of the line items in the plan were converted into task in TFS except for few which did not have resources assigned to it (milestones) and those which had more than one resource assigned. I am ok with these task not being published and hence i played along. After this, i did a refresh. As soon as i did this, all tasks which were published in TFS disappeared.
I am pretty upset as it was a huge plan and i dont have a backup. Can someone please help?
Thanks,
Atul
Atul
All Replies
-
Friday, June 22, 2012 1:36 PM
-
Friday, July 06, 2012 12:58 PM
Aquí te dejo un link de mi bloc donde se trata este tema.
http://alduar.blogspot.com.es/2012/07/mapiar-project-server-2010-con-tfs-2012.html
Saludos
-
Monday, July 30, 2012 11:01 AM
Aquí te dejo un link de mi bloc donde se trata este tema.
http://alduar.blogspot.com.es/2012/07/mapiar-project-server-2010-con-tfs-2012.html
Saludos
Here I leave a link to my bloc which addresses this issue.
http://alduar.blogspot.com.es/2012/07/mapiar-project-server-2010-con-tfs-2012.htmlOn my bloc you can use traslate Gatget
regards
Aldo Flores@alduar
-
Tuesday, July 31, 2012 9:06 PMOwner
Atul,
Are you using our Project Client Integration (From "Team" Ribbon) or the Project Server Integration. Looks from your action Client Integration.
Here is the forum for Client related question http://social.msdn.microsoft.com/Forums/en-US/tfsworkitemtracking/threads
Smitha Saligrama MSFT
- Marked As Answer by Ewald Hofman - TFS Product TeamMicrosoft Employee Tuesday, August 14, 2012 10:27 PM