Hi,
If the original principal is now in the sync/restoring state then at some point there has been a manual or automatic failover and the original mirror has taken on the role of principal.
You can manually failover the database so the original principal becomes the mirror but I would like to know why it failed over. Was there an outage? What is the config of the mirror session are you using high availability mode, etc?
http://msdn.microsoft.com/en-us/library/ms191449.aspx
http://msdn.microsoft.com/en-us/library/ms365781.aspx
http://msdn.microsoft.com/en-us/library/ms186348.aspx
Sean Massey | Consultant,
iUNITE
Feel free to contact me through
My Blog,
Twitter or
Hire Me.
Please click the Mark as Answer button if a post solves your problem!