Dear all,
we've created a recurring task (weekly on Monday, duration 1h, FixedUnits, no calendar set) and assigned same resources to all occurrencies. Now we checked the timesheets of those resources: timesheets for next week just list the occurrence of next week,
but not any incomplete occurrency of the current week (even if current timesheet is completely approved already).
Normally incomplete tasks are shown on timesheets until all work is done (or remaining work is set to 0). Is this different for recurring tasks? Our suspicion is that timesheets for next week are not completely generated today and incomplete occurrencies
will appear, but only next Monday. Kindly advice, if possible (otherwise we've to wait and see next Monday...)
Many thanks in advance