Custom Enterprise Field not update from My Task or My Timesheet

问题 Custom Enterprise Field not update from My Task or My Timesheet

  • Wednesday, July 25, 2012 9:49 PM
     
      Has Code
    
    
    I have created a Custom Enterprise Field using Lookup Table and I am add this field in Project Professional and on My Task and My Timesheet view. 
    I am able to edit and publish the Field from Project Professional and see the values under My Task. But if i update the value of the Enterprise resource from My Task or My Timesheet under PWA, it does not get reflected in the MS Project Professional. 
    
    My environment is MS Project Server 2010 SP1 CU Abril 2012 and client MS Project Professional SP1
    
    Please tour comments to resolve this behaviour
    
    Thanks 
    

All Replies

  • Wednesday, July 25, 2012 11:25 PM
     
     

    Take a look at the usage view in Project Professional. You may see it there as assignment level information is visible there.

    Custom fields are set at the Project, Task or Resource level.

    The relationship looks like Project --> Task -->Assignment (what you see on Tasks/Timesheet) <--Resources.

    Unless you enabled Rolldown on the server, the value is not pushed down to the Assignment level. When the value is updated at the assignment level on the Tasks or Timesheet view, it is NOT pushed up to the Task or Resource level value.

    Hopefully, this makes sense. It might be better if you share the problem you are addressing.

    Treb Gatte

  • Thursday, July 26, 2012 3:02 PM
     
     
    

    Hi Treb.

    The Enterprise Custom Field is  Task Level and is active "Roll down, unless manually specified" on "Calculation for Assignment Rows".

    Data (Lookup table) is visible in Task Usage View in Project Professional and I can to choose this values. But if I update the value of the Enterprise Custom Field from My Task or My Timesheet under PWA, it does not get reflected in the MS Project Professional.

    Do you have any idea for this behaviour?

    Thanks

  • Thursday, July 26, 2012 6:38 PM
     
     

    To confirm, the approval was processed and the project republished? If so, it should work.

    Treb Gatte

  • Thursday, July 26, 2012 8:54 PM
     
     
    Yes, the approval was processed and the update in Enterprise Custom Field is watched. After I open the project and insert the column with Enterprise Custom Field but the data approved not is here.
  • Tuesday, July 31, 2012 11:29 PM
     
     

    I'll have to play with this a bit.

    Treb Gatte

  • Wednesday, August 01, 2012 3:41 PM
     
     

    Treb,

    Thanks for your attention.

    I tried to check this behavior creating a new Enterprise Custom Field and new Timesheet View and the data is saved into the table MSP_TimesheetLine_UserViewCF but is not reflected in the corresponding field in MS Project Proffesional

    
    Any help thank you very much