Reporting period in one day
-
Tuesday, August 21, 2012 11:46 PMI need that staff fill out each days the comments and custom field for each task in the timesheet.
Is it right decision to use the reporting period in one day?
All Replies
-
Wednesday, August 22, 2012 3:25 AM
While there is no 'technical' challenge of using a "daily" reporting period, i think it is a lot of maintenance work to maintain that setting.
You might be better off considering a third-party tool like this: http://pinpoint.microsoft.com/en-us/applications/projectum-timesheet-daily-comments-12884937788
Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com
-
Wednesday, August 22, 2012 6:41 AMYes, I know about these solutions. But I need to, for example, to do custom field with constant values. Such a decision, I have never met. What's wrong with the solution with a period of one day?
-
Friday, August 24, 2012 7:36 PMLike I said, I cannot see anything wrong technically with one day time periods, other than maintenance and reporting.
Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

