many resources don't have the same schedule, can they start at the same time?
-
Friday, June 15, 2012 3:01 PM
How to make MS Project 2007 ensure many resources assigned to same task,and do not have the same schedule, begin the task at the same time?
I need resources that work concurrently on multiple tasks, it becomes very complex to do manually and I guess I could ask MS Project to do it automatically?Thank you for answers :)
All Replies
-
Friday, June 15, 2012 3:43 PM
Mireille,
We need more definitive information about your resource calendars. I assume your resource calendars simply have different work days but if their work start times are also different then they obviously won't have the same start time when assigned to tasks simultaneously.
John
-
Friday, June 15, 2012 3:47 PMModerator
Are you saying that you have a set of resources whose calendars dictate that they start at different times of the day but there is a task in your project where they all need to start at the same time regardless of their own resource calendars? If that is the case then you can set a task calenar for the task in the Task INformation dialog and then check the box next to it for "Ignore Resource Calendars". This will force project to assign the resources according to the task calendar start time NOT the individual resource calendars.
Brian Kennemer - Project MVP
DeltaBahn Senior Architect
endlessly obsessing about Project Server…so that you don’t have to.
Blog | Twitter | LinkedIn- Proposed As Answer by Sapna Shukla - Project MVPMVP, Moderator Monday, June 18, 2012 11:40 AM
- Marked As Answer by Mike GlenModerator Monday, August 13, 2012 7:07 PM