Microsoft Project 2010 RAG Status Indicators
-
Wednesday, May 09, 2012 7:39 AM
Hey Guys,
I have looked and looked and looked for how to write Microsoft Project RAG Status indicator formulas, but there is such conflicting posts, especially as this is a complex formula.
I want graphical indicators to represent the status of a task:
- Not Due to Start = White
- In progress and on track = Green
- Completed = Blue / Black
- At risk of being late (Less than 7 days to go and less than 50% completed) = Amber
- Late = Red
- Not Baselined = ‘?’
- Critical milestone / task indicator = tick of flag (may be in a difference formula
I have written so many formulas and they all get syntax errors or they do not represent what I want. Got any tips?
All Replies
-
Wednesday, May 09, 2012 8:53 AM
Hello Jack,
Try this:
IIf([Critical]="Yes","7",IIf([Baseline Finish]=4294967295,6,IIf([Baseline Finish]<[Finish],5,IIf([% Complete]=100,3,IIf([Start]<Now(),IIf([% Complete]>0,2,IIf([Finish]-Now()>7,IIf([% Complete]<50,4,1),1)))))))
Should you the number output as you set out in your list, which you can then convert to a graphic.
Thanks,
Andrew
-
Thursday, May 10, 2012 8:48 AM
HI Andrew,
I have tried that and unfortunately it is not working as well as I would like. It seems that the order is not working.
I have made my criteria a little easier.
- Not Due to Start = White
- In progress and on track = Green
- Completed = Blue
- At risk of being late (Less than 7 days to go and less than 50% completed) = Amber
-
Late = Red
My current formula is:
Switch([% Complete]=100,'BLUE',[Finish]>[Baseline Finish]+1,'RED',[Finish]<=[Baseline Finish]-1,'GREEN',[Finish Variance]<=0,"White",[Finish]<=[Baseline Finish]+1,'AMBER')
However it is only showing completed tasks (blue) and not due to start tasks (white) when there is clearly late (red) and At risk (amber) tasks on there.Any ideas?
-
Thursday, May 10, 2012 9:01 AMModerator
Hi,
I just want to clarify on Red and Amber scenario so that you can give a thought to it.
At risk of being late (Less than 7 days to go and less than 50% completed) = Amber - What if a task is just of 7 days or alike? Anything late means it has not reached to planned % Complete, reasons could be numerous. So, just wanted to understand the reason for "Amber" calculation.
Because a task of 17 days : say currently on 11th day shows 50% complete so it should be AMBER as per you, but looking logically its a Delayed task (should be at 65%) so nothing less then Red should go.
Sapna S
-
Thursday, May 10, 2012 9:07 AMHi Sapna,
There would have to be an exception in place. This might work better as a percentage.
So if a task has <20% of it's time left and has been <50% completed then it would be amber.
If you need further clarification let me know.
-
Thursday, May 10, 2012 9:54 AM
Hi Jack,
Had a quick bash at this, but to do it with a single field is going to be pretty convoluted with a beast of embedded if statements in there.
To make it easier to build (and maintain going forward), what I'd do is use flag fields for your indicators:
- Flag 1 - White
- Flag 2 - Green
- Flag 3 - Blue
- Flag 4 - Amber
- Flag 5 - RedYou'd give each flag field a formula to determine whether or not the conditions for that flag are true. The complexity that Sapna has identified could be factored into the formula for flag5
You'd then have a switch statement like you've got which assesses the flags in their order of precedence to determine what graphic should be used, which would need something like:
Switch(
[flag3]=true, "Blue",
[flag5]=true, "Red",
[flag4]=true, "Amber",
[flag1]=true, "White",
[flag2]=true, "Green",
1=1,"Error"
)I've got 1=1 at the end as a catch all if none of the other conditions are true - but if you structure the flag formulas correctly this should hopefully not fire.
Hope this is helpful,
Andrew
- Edited by Andrew Simpson Thursday, May 10, 2012 9:58 AM submitted before finished
-
Thursday, May 10, 2012 10:54 AMModerator
Adding to Andrew's comment that merging Red and Amber would lead to complex nested statements. We can work on it provide a fix criteria to differentiate between Red and Amber.
As of now making it short switch statement to track your -
- Not Due to Start = White
- In progress and on track = Green
- Completed = Blue
- Late = Red
Switch([Status]=3,"White",[Status]=0,"Blue",[Status]=1,"Green",[Status]=2,"Red")
Sapna S
- Marked As Answer by Sapna Shukla - Project MVPMVP, Moderator Thursday, June 14, 2012 6:23 AM
-
Tuesday, June 12, 2012 7:02 PM
Please see my recent blog entry for a pair of macros that create the sort of indicators you need:
http://blogs.captechconsulting.com/blog/tim-fite/i-love-my-status-symbols
- Proposed As Answer by Sapna Shukla - Project MVPMVP, Moderator Thursday, June 14, 2012 6:28 AM
-
Thursday, June 14, 2012 6:22 AMModerator
Hi Jack,
I'm closing the thread, re-open it if the suggested options doesn't help you.
Sapna S

