MSProject 2007 the use of filter to get only a range of free Slack listed in a a column question
-
Thursday, August 09, 2012 11:06 PM
Hi,
I am wondering if someone can help me write the command for getting only the tasks that have a free Slacks ranging from e.g. 3 and 7 Days? this Free Slack has already been integrated into the project Plan in a column. I tried to use a formula but did not work. In this column called Free Slacks may contains value variying from Negative values (-) to any Positive numbers.
Looking forward to hearing from you and thanks in advance!
Chuck
All Replies
-
Friday, August 10, 2012 12:38 AM
Hello Chuck,
I believe the following filter definition will do it:
Regards.
- Marked As Answer by chamdan Friday, August 10, 2012 9:10 PM
-
Friday, August 10, 2012 2:29 AM
Thanks for your prompt reply, I really appreciate your support. I guess this should work smoothly I will give it a try tomorrow.
Cheers!
Chuck
-
Friday, August 10, 2012 8:36 AMYou're welcome. --Regards.
-
Friday, August 10, 2012 9:11 PM
Thanks! it worked like a charm..
Regards,
Chuck
-
Friday, August 10, 2012 9:49 PMYou're welcome and thank you for the feedback. --Regards.