Factoring in rain delay to a construction project
-
Thursday, June 14, 2012 11:12 PMI have heard that some users will build in a rain delay factor into their project. What is the best way of doing this?
All Replies
-
Friday, June 15, 2012 1:43 AMModerator
that would be a hard one to estimate since you would never really know how long the delay would be so trying to factor it in ahead of time would be rough. As far as dealing with in in your schedule as the rain happens:
Lets assume you are in 2010.
Task A is a successor to task B. You have them linked. Now insert a task called Rain Delay between then. so that Rain delay is a successor to Task A and a predecessor to Task b and A and be are still linked. Now mark the Rain Delay task as Inactive. Then if it rains make it Active and then estimate the delay. This will then push out Task B.
Brian Kennemer - Project MVP
DeltaBahn Senior Architect
endlessly obsessing about Project Server…so that you don’t have to.
Blog | Twitter | LinkedIn- Proposed As Answer by Sapna Shukla - Project MVPMVP, Moderator Friday, June 15, 2012 8:14 AM
- Marked As Answer by fitzhay Saturday, June 23, 2012 12:15 AM
-
Friday, June 15, 2012 9:56 PMModerator
I would take a more generalist approach. Better to schedule each task as if the weather was good enough (but not perfect). Do some risk analysis. One risk is obviously rain will stop work. Calculate a contingency delay (not cost) in days and tehn add a contingency task to the area affected. For example a house build might have contingency for rain whilst constructing foundations, but not for interior work once the building is closed in.
Rain is just one risk that needs factoring in. If the rain doesn't happen, set actual duration to zero and remaining duration to zero (or Inactive if you have 2010 Pro). If more rain than expected happens then extend the contingency task. Your schedule now clearly shows where the delay occurred: in contingency task which for this part of the job is mostly from Rain. I assume your site diary will also record which days?
Rod Gill
The one and only Project VBA Book
Rod Gill Project Management
- Marked As Answer by fitzhay Saturday, June 23, 2012 12:15 AM
-
Saturday, June 23, 2012 12:21 AM
I have been away for a few days and have only now checked the site for answers. Thank you for your help. I hadn't thought of using the inactive feature in 2010.
Regards
fitzhay
-
Saturday, June 23, 2012 12:23 AM
Thanks for your help. I have been away for a few days and have only now had a chance to check the board for replies.
regards
fitzhay

