Respondida BCWP Not Updating on Project Server 2010 PDP

  • Tuesday, October 11, 2011 10:39 PM
     
     

    I have a PDP that I have configured to include CPI, SPI, BCWP, ACWP, EAC, VAC, and other fields.  Although all fields are updated and display properly in Project Pro, their behavior on the PDP is strange.  The CPI and SPI do not pull in values until the PDP is edited and saved.   More disappointing is that the BCWP value is never loaded into the field -- regardless of saving the PDP or otherwise.  I'm looking for insights into what may be going astray here, and what I need to investigate.  Thanks.

    Jim


    JB Fink

All Replies

  • Wednesday, April 11, 2012 4:16 PM
     
     

    Indeed, I have almost the same symptoms: (except CPI and SPI: theys are working properly...)

    (I did the test with CU Oct 2011)

    Regards
    Wim

  • Wednesday, May 16, 2012 7:47 PM
     
     

    Wim, have you had any luck in correcting the issue you're seeing?

    Jim


    JB Fink

  • Thursday, May 17, 2012 7:31 AM
     
      Has Code

    Jim & Wim,

    I had the similar issue on PS2010 (RTM , as well as SP1+June CU2011) PDP page which doesn't show BCWP/BCWS values on that. To troubleshoot more, Initially, I thought that data is not updated or corrupted in Published database so tested with few queries in Published/draft & Reporting. Unfortunatley, data was all correct but somehow while PDP page doesn't get that while loading.

    --In Reporting database
    select t.ProjectUID,p.ProjectName,t.TaskUID, t.TaskIndex, t.TaskACWP, t.TaskBCWP, t.TaskBCWS 
    from  dbo.MSP_EpmTask_UserView t
     JOIN MSP_EpmProject p
     ON t.ProjectUID = p.ProjectUID 
     where TaskBCWP<>0 AND TaskBCWS <>0
    AND p.projectUId = '84EEAB2E-B301-4529-8937-22CC6CA133DE'
    AND t.TaskIndex =0
    -- In published database
    SELECT A.PROJ_UID, A.PROJ_NAME, B.TASK_UID, b.Task_ID,B.TASK_NAME, B.TASK_ACWP, B.TASK_BCWP, B.TASK_BCWS
     FROM MSP_PROJECTS A, 
    MSP_TASKS B, MSP_TASK_BASELINES 
    WHERE A.PROJ_INFO_STATUS_DATE IS NOT NULL AND A.PROJ_UID = B.PROJ_UID 
    AND B.TASK_UID = MSP_TASK_BASELINES.TASK_UID 
    AND MSP_TASK_BASELINES.TB_BASE_NUM = 0 AND (task_outline_level LIKE '0') 
    AND A.PROJ_UID = '84EEAB2E-B301-4529-8937-22CC6CA133DE'

    Luckily, I was working on a customized pdp page, so I was able to pull the values in reporting store without any issues as a workaround.

    May be not lot of user reported this to Microsoft. Also, I have not tested this with Feb/Aril 2012 CU. Hope MS or someone who was able to do this, will provide an update. Just thought to provide a workaround not the fix.


    If you found this post helpful, Please "Vote as Helpful";. If it answered your question, Please "Mark as Answer".
    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82


  • Friday, May 18, 2012 3:55 PM
    Moderator
     
     

    You could always use an InfoPath query against the RDB as a workaround I suppose:

    http://azlav.umtblog.com/2011/05/04/making-a-read-only-pdp-with-infopath-forms/


    Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky

  • Friday, May 18, 2012 3:56 PM
    Moderator
     
     Answered

    Actually, come to think of it....

    Just create an Enterprise Custom Field called BCWP2 and set it to =[BCWP].  Add BCWP2 to the PDP.

    That might be a bit simpler. :-)


    Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky

  • Saturday, May 19, 2012 11:23 AM
     
     
    Agreed Andrew simple by using a calculated CF  but BCWP/ BCWS display seems to be bug? isn't it?

    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

  • Sunday, May 20, 2012 1:38 AM
    Moderator
     
     
    Sounds like a bug to me....

    Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky

  • Tuesday, May 22, 2012 10:34 PM
    Owner
     
     

    Sounds like it could be - but just a reminder that just mentioning on the forums doesn't mean that a 'bug' will miraculously be fixed in a future cumulative update.  If this is something you would like to see reviewed and potentially changed then best to leverage your Premier support contracts.  However, looks like there is at least a workaround for this one.

    Best regards,

    Brian.


    Blog | Facebook | Twitter | Posting is provided "AS IS" with no warranties, and confers no rights.
    Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page