Отвечено Sample Proposal Workflow get Automatically Approved

  • Wednesday, August 15, 2012 3:58 PM
     
     

    I'm having trouble getting the Sample Proposal Workflow working as expected, in my installation the Approval is automatically skipped, this is despite having populated the 'Portfolio Manager' group.

    "The proposal was automatically approved because the approvers' group has no members"

    is there anything else I have to do other than populate the Portfolio Manager group?

    Project Server 2010

    Thanks

    Saurabh

All Replies

  • Sunday, August 19, 2012 11:05 PM
    Moderator
     
     
    Do you have departments set up ? I am pretty sure the workflow will do a dept check and will skip if the dept filter yields no approvers.

    Alex Burton
    www.epmsource.com | Twitter
    Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page

  • Wednesday, August 22, 2012 7:48 PM
     
     Answered

    Saurabh,

    Alexander is correct.  In addition to housing the users in the Portfolio Managers group, be sure that your intended workflow approvers have the same Department value as the Enterprise Project Type being used (in your case, Sample Proposal).

    Even if a User or Enterprise Project Type has no department selected, that's considered it's value...no value.  So be sure to match the Department of your approvers, to your workflow Enterprise Project Type they will be using.

    Hope this helps.


    Chris Addis - MCTS