Resource usage and task finish date does not reflect the work and scheduling options. Pl

    Question

  • Hi, 

    My calender option is 7 hrs a day and scheduling option is "Fixed work". 

    My Problem & background 

    • I have 4 tasks [Task 1 = 7hrs, Task 3 = 8hrs, Task 4 = 7 hrs, Task 4 = 8hrs]
    • Task 3 having FS dependency on task 1 while task 4 has FS dependency on task 2 
    • Task 1 & 2 start on 17th March by Resource 1 and Resource 2 respectively 
    • Gant chat view shows that Task 1 finishes on 17th itself and Task 3 also starts on 17th it self. Also Task 2 start on 17th and finishes on 17th while task 4 start on 18th. 
    • When i look at the resource usage each resource work 8 hrs day

    My questions 

    • If I have defined 7hr work day: why resource usage shows 8 hrs per day, should not it be 7 hrs Max per day
    • Also, if a work day is 7 hrs, why task 2 [8rs] end day is shown as 17th itself where it should be 18th Tuesday [7 hrs on 17th and 1 hr on 18th]

    I'm concern even if we set the option as 7hrs work day [35 hrs week], does MS project still use 8hr work day. What options we have to make it 7 hrs work day and 35 hrs work week which is our productive week. 

    Can someone please help me to clarify the above. 

    Saturday, March 15, 2014 6:52 AM

Answers

  • Hi Harsha,

    Please refer to this post:

    http://ntrajkovski.com/2013/12/11/scheduling-problem-in-ms-project-2013/

    You have to set the same working time in both project calendar working week hours and MS Project schedule options.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    • Marked as answer by Harsha K Sunday, March 16, 2014 12:54 PM
    Saturday, March 15, 2014 4:31 PM

All replies

  • Hi Harsha,

    Please refer to this post:

    http://ntrajkovski.com/2013/12/11/scheduling-problem-in-ms-project-2013/

    You have to set the same working time in both project calendar working week hours and MS Project schedule options.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    • Marked as answer by Harsha K Sunday, March 16, 2014 12:54 PM
    Saturday, March 15, 2014 4:31 PM
  • Thank you Guilaume, it helped me to find the solution for my problem. 

    We could change the default work week - working time and achieve what I wanted to achieve. 

    Steps to do this

    - Click the "Project Menu" -> then click "Change Work Time" 

    - From the pop up, select the "Work week" tab 

    - Select the "default" and click "Details" button

    - Select the day you want to change the work time 

    - Select the "3rd option" - Set days to these specific working times 

    - Specify the working times as you wish

    - repeat it for all working days. 

    now it takes my working day as 7 hrs.

    Sunday, March 16, 2014 2:54 AM
  • You're more than welcome!

    Please mark the reply as an answer if it indeed gives you the clue.

    Cheers.


    Guillaume Rouyre - MBA, MCP, MCTS

    Sunday, March 16, 2014 4:10 AM